Location: The project begins at the intersection of Ready Section Rd. and Butter & Egg Rd. and runs east to the intersection of Ready Section Rd. and Loveless Rd. The total project length is 1.5 miles.
Project Description: The project includes the installation of 8,000ft of ductile-iron pipe to replace existing distribution mains. Customer water services will be transferred to the new main, once installed. Repairs to roadway surfaces, driveways, and landscaping will be completed as the project progresses and after the bulk of the water main installation is complete. There may be temporary impacts to traffic routing due to lane closures as the work progresses.
Project Timeline: The project is expected to begin in February 2025 and be completed by July 2025.
Need for Project: This project replaces aging water main along Ready Section Rd that has seen numerous main breaks in recent years. This new line will also provide more reliable transmission from the Hazel Green Well to our customers.
Questions: For any additional questions on this project call Vince Moody (256)783-1547 (7AM-3:30PM) or email at vmoody@madisoncountyal.gov.