Home MenuButter & Egg Rd Main Improvement
Location: The project runs along Butter & Egg Rd from Charity Ln to Ed Baeder Rd. The total project length is about 3/5 mile.
Project Description: The project includes the installation of 3100 ft of new PVC pipe to replace existing mains. Customer water services will be transferred to the new main, once installed. Repairs to roadway surfaces, driveways, and landscaping will be completed as the project progresses and after the bulk of the water main installation is complete. There may be temporary impacts to traffic routing due to lane closures as the work progresses.
Project Timeline: The project is expected to begin in Spring 2024 and be completed by Summer 2025.
Need for Project: This project replaces aging water main along Butter & Egg Rd that has seen numerous main breaks in recent years.