Banyon Rd Main Upgrade

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Location: The project runs the entire length of Banyon Rd in Toney, AL. The total project length is about 1 mile.

Project Description: The project includes the installation of 5300 feet of PVC and Ductile Iron pipe to replace existing mains. Customer water services will be transferred to the new main, once installed. Repairs to roadway surfaces, driveways, and landscaping will be completed as the project progresses and after the bulk of the water main installation is complete. There may be temporary impacts to traffic routing due to lane closures as the work progresses.

Project Timeline: The contract is expected to be awarded at the end of November 2024. 

Need for Project: This project replaces aging water main along Banyon Rd that has seen numerous main breaks in recent years.

Questions: For any additional questions on this project call Phillip McDoniel (256)932-6056 (7AM-3:30PM) or email at pmcdoniel@madisoncountyal.gov.